Feb 8, 2013 ... We have now finished setting up the site and have begun treatment of the Chalk Mines. Below are images from the camera that was sent down ...
https://www.dacorum.gov.uk/.../bam-ritchies-newsletter-01---bulk-infilling....
Dear. HIGHBARNS CHALK MINE – PROGRESS UPDATE. Please find attached notes of the latest meeting with The Residents Group that took place on 26 March.
https://www.dacorum.gov.uk/docs/default.../23-4-highbarns-lett.pdf?...0
that the mines may extend to). The geophysical survey has indicated the general location of the mines, so significant changes to the mine layout are not ...
https://www.dacorum.gov.uk/.../highbarns-qa-table---november-2011x.pdf...
May 3, 2013 ... So far, the extent of the mine model has proven to be very accurate. Parts of the central area have been completed, with properties on Pond ...
https://www.dacorum.gov.uk/.../bam-ritchies-newsletter-no-4-nbsp---may-2...
Dec 20, 2013 ... ... Ritchies. Above is a Rockworks image of dynamic probe VP104 taken from the Highbarns Chalk Mine Remediation project on East Green.
https://www.dacorum.gov.uk/.../bam-rithchies-newsletter-10---christmas-13...
Mar 5, 2013 ... To date we have placed approximately 1100m3 of cement grout into open void mine shafts, which is equivalent in volume to about 11 double decker ...
https://www.dacorum.gov.uk/.../bam-ritchies-newsletter-no-2---march-201...
Oct 5, 2009 ... The second stage requires crucial detailing of facts including the history of the mines, planning consents, environmental regulations, hence DBC ...
https://www.dacorum.gov.uk/.../minutes-of-highbarns-public-meeting-held...
Feb 7, 2014 ... You will be pleased to know that the chalk mine works are all but complete within the DLCO. We have placed over 8300m3 of bulk and ...
https://www.dacorum.gov.uk/docs/.../newsletter-11---february-14.pdf?...0
Jan 7, 2013 ... As you will be aware, Since 2007 Dacorum Borough Council has been working with residents to treat an abandoned chalk mine that was responsible.
https://www.dacorum.gov.uk/.../compounds-letter---chambersbury-lane-7-j...
Jul 15, 2013 ... HIGHBARNS CHALK MINE – CONTINUATION OF WORKS. Following my letter of 22 April and the public meeting held on Thursday 4 July. 2013, I can ...